List of questions
Related questions
Question 1409 - PMP discussion
A bridge construction project has been paused due to a political change in the local government.
After almost 5 years, the new government would like to resume the project, and a project manager is assigned.
What should the project manager do first?
A.
Prepare an estimate of the time and cost to complete this project.
B.
Study the project's lessons learned to understand why it was paused.
C.
Meet the new stakeholders and understand their expectations.
D.
Examine the project's business case in order to resume the project.
Your answer:
0 comments
Sorted by
Leave a comment first