The stakeholders in an agile project are upset because some of the final products do not meet their expectations. When the project manager asks the team about the stakeholders' expectations, the team only mentions the project's objective.

In addition to reminding the team about the importance of stakeholder expectations, interest, and influence in the project, how should the project manager improve this situation?

A.

Motivate the team to create and use an agile project charter.

Answers
A.

Motivate the team to create and use an agile project charter.

B.

Encourage the team to use an information radiator to analyze expectations.

Answers
B.

Encourage the team to use an information radiator to analyze expectations.

C.

Teach the team how to use the user persona technique.

Answers
C.

Teach the team how to use the user persona technique.

D.

Remind the team that face-to-face communication is the best method.

Answers
D.

Remind the team that face-to-face communication is the best method.

Suggested answer: C