Question 1411 - PMP discussion
During the execution phase of a project, a new project manager is assigned to replace the previous project manager. As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past.
What should the project manager do next to improve this situation?
Review the resource management plan and organizational assets.
Estimate the baseline impacts and submit a change request.
Implement compression techniques to bring the project back on track.
Call for a team meeting to identify the root cause for the declining performance.