A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint.

A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

A.

Document the lessons learned and implement improvements in the next sprint.

Answers
A.

Document the lessons learned and implement improvements in the next sprint.

B.

Request that all team members think of ideas to improve processes.

Answers
B.

Request that all team members think of ideas to improve processes.

C.

Facilitate a daily standup with the team to track the implementation of changes.

Answers
C.

Facilitate a daily standup with the team to track the implementation of changes.

D.

Organize a demonstration of the changes in the enterprise system.

Answers
D.

Organize a demonstration of the changes in the enterprise system.

Suggested answer: A