Question 1417 - PMP discussion

Report
Export

A project manager brings in a new team member from an agile environment to work in a predictive environment. The project manager expects to leverage the new team member's agile experience with the existing team members.

What should the project manager do to integrate the new team member effectively?

A.

Set expectations with the new team member and explain what is needed.

Answers
A.

Set expectations with the new team member and explain what is needed.

B.

Acknowledge that hiring this new employee is a risk to the existing team.

Answers
B.

Acknowledge that hiring this new employee is a risk to the existing team.

C.

Train the new team member in the predictive project management approach.

Answers
C.

Train the new team member in the predictive project management approach.

D.

Meet with all team members and explain the new employee's position.

Answers
D.

Meet with all team members and explain the new employee's position.

Suggested answer: A