Question 1418 - PMP discussion
Upon analyzing the report requirements to create a functional design, the project team finds that the information source is not correct and needs to be adjusted. What should the project manager do?
A.
Initiate a change request procedure.
B.
Build a prototype to verify the information.
C.
Consult with subject matter experts (SMEs).
D.
Review the statement of work (SOW).