Upon analyzing the report requirements to create a functional design, the project team finds that the information source is not correct and needs to be adjusted. What should the project manager do?

A.

Initiate a change request procedure.

Answers
A.

Initiate a change request procedure.

B.

Build a prototype to verify the information.

Answers
B.

Build a prototype to verify the information.

C.

Consult with subject matter experts (SMEs).

Answers
C.

Consult with subject matter experts (SMEs).

D.

Review the statement of work (SOW).

Answers
D.

Review the statement of work (SOW).

Suggested answer: C