Question 1419 - PMP discussion
The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.
What should the project manager do first in this situation?
A.
Provide the specifications to the project sponsor with some information removed.
B.
Update the issue log to make the project team aware and to develop a strategy.
C.
Create a stakeholder engagement plan to help the team formulate a response.
D.
Meet with the project sponsor as soon as possible to discuss the matter further.
Your answer: