A developer who has almost completed a required product feature for a prototype leaves the company in the middle of an iteration. What should the project manager do?

A.

Go to management and ask to hire a new external developer.

Answers
A.

Go to management and ask to hire a new external developer.

B.

Review the backlog to reschedule the deliverable for a later iteration.

Answers
B.

Review the backlog to reschedule the deliverable for a later iteration.

C.

Determine whether other cross-functional team members are able to take over the work.

Answers
C.

Determine whether other cross-functional team members are able to take over the work.

D.

Engage with stakeholders directly to review the iteration process.

Answers
D.

Engage with stakeholders directly to review the iteration process.

Suggested answer: C