An agile project has a documented list of requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.
What should the project manager recommend?
Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.
Ensure the product owner determines the priority based on a product roadmap, release plan, and iteration plan.
Ask the team to prioritize the high-priority items based on the release plan and what allows for testing most effectively.
Discard the current categorization of requirements as "high, medium, and low" and prioritize numerically.