Question 1449 - PMP discussion
A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity.
What management decision is suited for this situation?
A.
Move team members who are not performing from the team.
B.
Add new members to the team and increase the velocity.
C.
Re-assign the project to a team that has worked with this technology.
D.
Provide opportunity for team members to learn and adjust to the technology.