A project manager's transformation project has been delayed due to unexpected issues with the information technology (IT) systems. These issues are likely to impact the project budget, but the project manager is working hard to make ensure there is no impact on the project's schedule and scope.

Which two actions should the project manager take before proposing a budget rebaseline to upper management for approval? (Choose two.)

A.

Consider schedule compression techniques to shorten or accelerate the schedule duration without reducing the project scope.

Answers
A.

Consider schedule compression techniques to shorten or accelerate the schedule duration without reducing the project scope.

B.

Consider using resource leveling to more accurately reflect the work commitments of the resources.

Answers
B.

Consider using resource leveling to more accurately reflect the work commitments of the resources.

C.

Apply data analysis techniques, variance analysis, and trend analysis.

Answers
C.

Apply data analysis techniques, variance analysis, and trend analysis.

D.

Analyze the budget based on the revised estimates and responses from similar situations in the past.

Answers
D.

Analyze the budget based on the revised estimates and responses from similar situations in the past.

E.

Raise a change request with high priority to be discussed in the upcoming governance meetings.

Answers
E.

Raise a change request with high priority to be discussed in the upcoming governance meetings.

Suggested answer: C, D