A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.
Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions.
Recognize the stakeholder's skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.
Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.