Question 1462 - PMP discussion

Report
Export

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations.

What steps should the project manager have taken to prevent this?

A.

Ensure the team understands all additional project requirements.

Answers
A.

Ensure the team understands all additional project requirements.

B.

Ensure the team receives continuous feedback from customers/users.

Answers
B.

Ensure the team receives continuous feedback from customers/users.

C.

Update the project management plan in order to get back on track.

Answers
C.

Update the project management plan in order to get back on track.

D.

Submit a change request to adjust the project scope.

Answers
D.

Submit a change request to adjust the project scope.

Suggested answer: A
asked 12/11/2024
Rodwell Shibambu
51 questions
User
Your answer:
0 comments