Question 1463 - PMP discussion

Report
Export

A project has recently kicked off. The project manager observes that there are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project manager use as a guide to resolve the issue?

A.

Project organization charts

Answers
A.

Project organization charts

B.

Project charter

Answers
B.

Project charter

C.

Stakeholder register

Answers
C.

Stakeholder register

D.

Team charter

Answers
D.

Team charter

Suggested answer: D