After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?

A.

Ahead of schedule

Answers
A.

Ahead of schedule

B.

On schedule

Answers
B.

On schedule

C.

Behind schedule

Answers
C.

Behind schedule

D.

Stopped

Answers
D.

Stopped

Suggested answer: C