A product owner feels that the last sprint tailed to sufficiently deliver what was valuable to the>r organization's overall project goals What should the scrum master mention at the next retrospective?

A.
Solutions to project problems that were built into the last sprint
Answers
A.
Solutions to project problems that were built into the last sprint
B.
Problems that arose
Answers
B.
Problems that arose
C.
Solutions that saved that organization the most time and money
Answers
C.
Solutions that saved that organization the most time and money
D.
Problems that were solved
Answers
D.
Problems that were solved
Suggested answer: A