A project is 70% complete when the project sponsor requests an additional deliverable.

What should the project manager do first?

A.
Negotiate with the project sponsor on the possible alternatives
Answers
A.
Negotiate with the project sponsor on the possible alternatives
B.
Determine the possible impact of this change on all aspects of the project
Answers
B.
Determine the possible impact of this change on all aspects of the project
C.
Reject the request as being too late and leading to major scope creep
Answers
C.
Reject the request as being too late and leading to major scope creep
D.
Submit the request to the change control board (CCB) for a decision
Answers
D.
Submit the request to the change control board (CCB) for a decision
Suggested answer: B