Question 15 - PMP discussion
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach. This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?
A.
Asked the sponsor to identify all required skills during the planning of the project
B.
Identified all required skills after the kick-off of the project
C.
Planned all required training for the team during the onboarding process
D.
Identified all required skills during the planning of the project