One phase of a project took much longer than initially anticipated. The key stakeholders expressed their concern regarding a potential project delay.

What should the project manager do?

A.
Request additional contingency from the sponsor
Answers
A.
Request additional contingency from the sponsor
B.
Add more float to the overall project schedule
Answers
B.
Add more float to the overall project schedule
C.
Expedite the next phase to reduce slippage
Answers
C.
Expedite the next phase to reduce slippage
D.
Organize a root cause analysis (RCA) workshop
Answers
D.
Organize a root cause analysis (RCA) workshop
Suggested answer: D