ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 25 - PMP discussion

Report
Export

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country's unique requirements. The expected revenue for the product is the same for each country.

Which release strategy should the project manager recommend?

A.
An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country
Answers
A.
An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country
B.
A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time
Answers
B.
A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time
C.
A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity
Answers
C.
A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity
D.
A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues
Answers
D.
A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues
Suggested answer: A
asked 23/09/2024
Johannes Bickel
55 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first