A primary stakeholder is unable to join the project status meetings consistently. The project manager has been communicating with this stakeholder informally and regularly to ensure that the stakeholder is up to date on the project.
However, the project manager has recently resigned and will not be meeting with the new project manager prior to departure.
How should the project manager ensure that the new project manager continues to update this particular stakeholder?
A.
Ensure that the project team has been provided guidance on the specific needs of this stakeholder
B.
Update the stakeholder engagement plan with the specific communication needs for the stakeholder
C.
Ensure that the project documents contain specific instructions regarding the stakeholder
D.
Update the communications management plan with specific information on stakeholder engagement