A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

A.
Provide feedback to the team using project performance evaluations.
Answers
A.
Provide feedback to the team using project performance evaluations.
B.
Include buffer time in the schedule to absorb future delays.
Answers
B.
Include buffer time in the schedule to absorb future delays.
C.
Escalate the impact on the schedule to the project sponsor.
Answers
C.
Escalate the impact on the schedule to the project sponsor.
D.
Create a change request to extend the project's duration and costs.
Answers
D.
Create a change request to extend the project's duration and costs.
Suggested answer: A