A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.
Which measure should mitigate the impact of this key resource's departure?
A.
Establish a proactive knowledge-sharing plan
B.
Offer a new contract to the resource who is leaving
C.
Develop a contingency budget to replace the key resource
D.
Update the risk register and inform the customer