Question 35 - PMP discussion
A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins to identify, evaluate, and categorize the stakeholder relationships to the program.
What is the purpose of this process?
A.
Identify all stakeholders who can positively affect the project
B.
Identify all stakeholders who can negatively affect the project.
C.
Incorporate the needs of all stakeholders into the communications management plan
D.
Incorporate only primary stakeholders into the communications management plan