A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition process for upcoming projects.

What should the project manager do to ensure the project scope is completely defined?

A.
Meet with the general manager and convince them to return to using predictive approaches to avoid any risk
Answers
A.
Meet with the general manager and convince them to return to using predictive approaches to avoid any risk
B.
Ask the general manager to review every requirement to ensure all projects will deliver the requested products
Answers
B.
Ask the general manager to review every requirement to ensure all projects will deliver the requested products
C.
Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements
Answers
C.
Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements
D.
Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations
Answers
D.
Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations
Suggested answer: D