A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.
What should the project manager do next?
A.
Hire a company in country B to perform a quality check before shipment
B.
Evaluate the procurement contract to determine the agreed-upon specifications
C.
Escalate the issue to the purchasing department for review
D.
Add an additional task to cut the received part according to the specifications