A project manager has team members around the world in many different time zones. Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.
What should the project manager have done to avoid this?
A.
Ensured that the project would be the highest priority for all team members
B.
Planned and scheduled tasks and work packages to overcome geographical and time zone challenges
C.
Learned more about how each team member prefers to communicate before assigning project work
D.
Used communication tools, such as video conferencing, so different offices could communicate