The project manager is reviewing a project's progress and notices that one of the risks has become an issue.
What should the project manager do to address the situation?
A.
Initiate a change request to obtain additional funds from the management reserve
B.
Meet with the project team and customer to brainstorm about potential solutions
C.
Schedule a high-priority meeting with the project stakeholders to discuss the issue
D.
Collaborate with the relevant stakeholders on implementing the risk response plan