Question 46 - PMP discussion
A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?
A.
During the planning phase, when processes for scope definition and activity duration and sequencing will be performed
B.
Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated
C.
In the initiation process, as it happens concurrently with the project contract and project charter creation
D.
As soon as possible, as project delays can be significantly avoided when a schedule is developed early