Question 47 - PMP discussion
After conducting a performance assessment, the project manager identified that some gaps still exist.
What should the project manager ensure?
A.
Awards are given to all team members for playing a role in the project and undertaking the assessment.
B.
Performance improvement programs are organized for all team members who were assessed.
C.
All team members rotate their job schedules immediately to make them versatile.
D.
Assessment results are kept private and not shared among team members.
Your answer: