Question 49 - PMP discussion

Report
Export

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

A.
Inform the product owner
Answers
A.
Inform the product owner
B.
Inform the project sponsor
Answers
B.
Inform the project sponsor
C.
Inform the relevant stakeholders
Answers
C.
Inform the relevant stakeholders
D.
Inform the project team only
Answers
D.
Inform the project team only
Suggested answer: C