Question 50 - PMP discussion
A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of the team.
What should the project manager do?
A.
Ask the team member to bring up the concern in the next daily meeting
B.
Send an email explaining the issue to all team members
C.
Reassign the task to another team member
D.
Move the task to the next sprint
Your answer: