Question 56 - PMP discussion

Report
Export

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change requests issued due to the nature of the project.

What should the project manager do?

A.
Reduce the number of approvers required to implement a change request
Answers
A.
Reduce the number of approvers required to implement a change request
B.
Request sponsor approval for all change requests to reduce the number of changes
Answers
B.
Request sponsor approval for all change requests to reduce the number of changes
C.
Initiate the number of iterations to reduce the number of change requests
Answers
C.
Initiate the number of iterations to reduce the number of change requests
D.
Add a fixed number of change requests allowed by the client on the project baseline
Answers
D.
Add a fixed number of change requests allowed by the client on the project baseline
Suggested answer: C