Question 57 - PMP discussion
A project manager is starting a new project, and the project team is located in different countries.
The team was going to use a specific tool to hold virtual meetings. However, that tool is not available in one team member's country.
How should the project manager deal with this situation?
A.
Contact the project sponsor to have the team member removed from the project
B.
Ask the team member to move to another location where the tool is available
C.
Investigate alternative tools for virtual meetings that are available to all team members
D.
Start the project and use email to communicate with the team member until the tool is available
Your answer:
0 comments