Question 63 - PMP discussion

Report
Export

A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders.

What should the project manager do to get this information?

A.
Identify each stakeholder's motivations from the business case.
Answers
A.
Identify each stakeholder's motivations from the business case.
B.
Request stakeholders articulate their motivations at the kick-off meeting.
Answers
B.
Request stakeholders articulate their motivations at the kick-off meeting.
C.
Email project objectives to all stakeholders and ask for endorsement.
Answers
C.
Email project objectives to all stakeholders and ask for endorsement.
D.
Organize a one-on-one conversation with each stakeholder.
Answers
D.
Organize a one-on-one conversation with each stakeholder.
Suggested answer: D