Question 64 - PMP discussion
During a project's initiation phase, a lessons learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.
What should the project manager do next?
A.
Discuss this issue with the project sponsor to request additional funding to implement mitigation
B.
Prequalify contractors with proven track records to eliminate productivity concerns
C.
Add construction productivity to the risk register and develop a mitigation strategy for site execution
D.
Hire a construction management consultant to develop a comprehensive site execution plan
Your answer: