During a project's initiation phase, a lessons learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.

What should the project manager do next?

A.
Discuss this issue with the project sponsor to request additional funding to implement mitigation
Answers
A.
Discuss this issue with the project sponsor to request additional funding to implement mitigation
B.
Prequalify contractors with proven track records to eliminate productivity concerns
Answers
B.
Prequalify contractors with proven track records to eliminate productivity concerns
C.
Add construction productivity to the risk register and develop a mitigation strategy for site execution
Answers
C.
Add construction productivity to the risk register and develop a mitigation strategy for site execution
D.
Hire a construction management consultant to develop a comprehensive site execution plan
Answers
D.
Hire a construction management consultant to develop a comprehensive site execution plan
Suggested answer: C

Explanation:

The learning from prior project was about construction productivity. So in order to prevent it happen in a new project, it has to monitored with a mitigation plan.

Explanation: