Question 65 - PMP discussion
A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact project implementation.
What should the project manager do next?
A.
Assign an additional resource to help the team member with the tasks
B.
Ask the team member's functional manager if there are any known issues
C.
Convene a team meeting to encourage and motivate the entire team
D.
Meet with the team member to understand their concerns and/or issues
Your answer: