Question 70 - PMP discussion

Report
Export

There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.

How should the project manager handle this situation?

A.
Counsel both team members and caution them with a final warning.
Answers
A.
Counsel both team members and caution them with a final warning.
B.
Relocate the two project team members into different project teams.
Answers
B.
Relocate the two project team members into different project teams.
C.
Escalate the issue to the human resources (HR) manager before a larger problem develops.
Answers
C.
Escalate the issue to the human resources (HR) manager before a larger problem develops.
D.
Help cultivate self-awareness between the two team members through emotional intelligence (EI).
Answers
D.
Help cultivate self-awareness between the two team members through emotional intelligence (EI).
Suggested answer: D