A few virtual team members are located in a region that generally has good internet connectivity.

However, they frequently experience connectivity issues joining team calls during the day.

What should the project manager do?

A.
Determine what the problem is and develop an action plan
Answers
A.
Determine what the problem is and develop an action plan
B.
Ask the team members to use chat tools as an alternative to calls
Answers
B.
Ask the team members to use chat tools as an alternative to calls
C.
Procure tools that consume less bandwidth for internet calls
Answers
C.
Procure tools that consume less bandwidth for internet calls
D.
Record the meeting to share with the team members who were unable to join
Answers
D.
Record the meeting to share with the team members who were unable to join
Suggested answer: A