Question 73 - PMP discussion
A project manager finds it challenging to comply with standardized processes for knowledge transfer. The project teams and stakeholders are scattered around field sites, the office, and remote locations. In addition, some team members have limited access to the electronically shared files.
How should the project manager manage this challenge?
A.
Study the environment and the available resources to determine which approach to use.
B.
Send the intended information through email since it is the primary communication tool.
C.
Communicate a strong message to the team explaining the importance of knowledge transfer.
D.
Request changes in the processes since it is not suitable for the company environment.
Your answer: