Question 74 - PMP discussion
During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B.
What should the project manager do?
A.
Ask team B to focus on their backlog and deliver based on their priority
B.
Inform team B of the dependency and ensure that the deliverable is planned
C.
Make team A a part of team B and ensure that the deliverable is ready
D.
Request team B to immediately start this activity and deliver to team A
Your answer: