ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 75 - PMP discussion

Report
Export

A large construction project is progressing well as per the project objectives. The project manager would like to report the project's value to the project sponsor and seek the next phase of funding closure.

What should the project manager do?

A.
Ensure a measurement system is in place like earned value analysis (EVA) to track project value for the project sponsor
Answers
A.
Ensure a measurement system is in place like earned value analysis (EVA) to track project value for the project sponsor
B.
Create a detailed project report on successes and challenges for the project sponsor
Answers
B.
Create a detailed project report on successes and challenges for the project sponsor
C.
Submit a detailed report on the cost budget vs. the cost actuals as the project sponsor will want to know more about finances
Answers
C.
Submit a detailed report on the cost budget vs. the cost actuals as the project sponsor will want to know more about finances
D.
Arrange a site visit to show the project sponsor the construction progress in person
Answers
D.
Arrange a site visit to show the project sponsor the construction progress in person
Suggested answer: A
asked 23/09/2024
Juan Carlos Delgado
37 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first