A project manager is managing a project that is halfway through its execution phase, and the quality standards of the deliverables were formally accepted.

However, a government agency has recently introduced new standards that may significantly impact the project. The deliverables must be changed to align with the new quality standards.

What should the project manager do?

A.
Schedule training for the project team on the new regulations introduced by the government agency
Answers
A.
Schedule training for the project team on the new regulations introduced by the government agency
B.
Set up a structured, independent processes to determine if project activities followed the standards
Answers
B.
Set up a structured, independent processes to determine if project activities followed the standards
C.
Update the lessons learned register and inform senior management of the new standards
Answers
C.
Update the lessons learned register and inform senior management of the new standards
D.
Evaluate the impact the new regulations will have on the project and submit a change request
Answers
D.
Evaluate the impact the new regulations will have on the project and submit a change request
Suggested answer: D