A project team's performance is being impacted by impeding internal procedures that are affecting the progress of activities and team autonomy.

What should the project manager do first to address this situation?

A.
Discuss the issue in the next sprint review meeting
Answers
A.
Discuss the issue in the next sprint review meeting
B.
Train the team members on the organization's procedures
Answers
B.
Train the team members on the organization's procedures
C.
Ask the organization to improve the internal procedures
Answers
C.
Ask the organization to improve the internal procedures
D.
Try to remove the barriers and empower team members
Answers
D.
Try to remove the barriers and empower team members
Suggested answer: D