A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.

What should the project manager do next?

A.
Immediately discuss this with the project sponsor and request to revisit the budget to ensure its accuracy
Answers
A.
Immediately discuss this with the project sponsor and request to revisit the budget to ensure its accuracy
B.
Add the missing budget items to the risk log and present them in the next project steering committee
Answers
B.
Add the missing budget items to the risk log and present them in the next project steering committee
C.
Start the project and deal with these budget issues as they arise throughout the project life cycle
Answers
C.
Start the project and deal with these budget issues as they arise throughout the project life cycle
D.
Reduce the quality and cost of other deliverables to allow additional budget for the items that were missed
Answers
D.
Reduce the quality and cost of other deliverables to allow additional budget for the items that were missed
Suggested answer: A