ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 83 - PMP discussion

Report
Export

A project schedule risk has turned into an issue. The project manager foresees delays in project execution.

What should the project manager do to resolve the issue?

A.
Escalate the issue to senior leadership for resolution
Answers
A.
Escalate the issue to senior leadership for resolution
B.
Work with relevant stakeholders to determine possible solutions
Answers
B.
Work with relevant stakeholders to determine possible solutions
C.
Update the schedule baseline to the new project time line
Answers
C.
Update the schedule baseline to the new project time line
D.
Update the risk management plan and send it to the project team
Answers
D.
Update the risk management plan and send it to the project team
Suggested answer: B
asked 23/09/2024
Anthony Wilson
42 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first