A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.

What should the project manager do about this risk?

A.
Review the supplier's contract to understand the terms of sale
Answers
A.
Review the supplier's contract to understand the terms of sale
B.
Insist that the supplier deliver the goods on the agreed date
Answers
B.
Insist that the supplier deliver the goods on the agreed date
C.
Update the risk register and take advantage of the opportunity
Answers
C.
Update the risk register and take advantage of the opportunity
D.
Accept the risk and update the risk register
Answers
D.
Accept the risk and update the risk register
Suggested answer: C