A project manager is assigned to manage a project for a previous client of the company. The project manager was warned that this client will likely try to add extra scope to the project without considering the impact of change on time, cost, quality, and risks.

Which action should the project manager take to help plan and manage the budget and resources?

A.
Refuse to allow the client to change the scope and examine the lessons learned register.
Answers
A.
Refuse to allow the client to change the scope and examine the lessons learned register.
B.
Decompose the deliverables into work packages and review the project charter.
Answers
B.
Decompose the deliverables into work packages and review the project charter.
C.
Create tight scope statements and review the historical information.
Answers
C.
Create tight scope statements and review the historical information.
D.
Include a scope change process and review the project charter.
Answers
D.
Include a scope change process and review the project charter.
Suggested answer: D