Question 107 - PMP discussion
A key stakeholder has recently started in a company and has been assigned to a hybrid project.
Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.
What should the project manager do?
A.
Inform the project management office (PMO) that the team will use a predictive approach for this project
B.
Inform the stakeholder that they must level their knowledge with other stakeholders
C.
Allocate time to mentor the stakeholder in the selected project approach
D.
Update the risk register with the potential impact and apprise the steering committee