A senior manager attends one of the project review meetings and expresses concern that the project will not meet the quality standards.

What should the project manager do?

A.
Ask the senior manager to approve the user acceptance testing (UAT) plan
Answers
A.
Ask the senior manager to approve the user acceptance testing (UAT) plan
B.
Inform the senior manager that there are approved quality standards
Answers
B.
Inform the senior manager that there are approved quality standards
C.
Review the quality management plan with the senior manager
Answers
C.
Review the quality management plan with the senior manager
D.
Estimate the backlog items to forecast quality
Answers
D.
Estimate the backlog items to forecast quality
Suggested answer: C